Sys-Tek provided commissioning, testing, adjusting, and balancing services for the mechanical equipment, and building automation systems (BAS) control for this 40,000 square foot Army Reserve Center. The systems balancing and commissioning included chillers, boilers with associated pumping and distribution systems, air handling units, traditional variable volume systems, terminal units including VAV boxes, fan coil units, unit heaters, exhaust fans, and temperature control systems.
As the commissioning agent, Sys-Tek developed and documented the functional testing procedures for the controls and equipment. We executed the functional tests for the air handling systems, hot water, and chilled water systems with the assistance of installing contractors when required. The installing contractors implemented required corrections to the equipment and control sequence programming after approved from the CX agent and owner’s representative. Implemented corrections were verified by retesting of the specific sequence.
In the design phase, we documented the design intent, and continued through construction, acceptance, and supported these efforts during the warranty period. Commissioning services during construction included the following specific objectives: